Context
The Hinchingbrooke Hospital Redevelopment Programme is a £1B+ scheme delivered under an NEC contract. Like most programmes its RAID log lived in a spreadsheet, maintained by several people, read by many more.
Problem
A flat list answers “what risks do we have”. A Programme Board asks different questions. What changed since last month. Which risks are getting worse despite mitigation. Where ownership is concentrated. What the aggregate exposure is by workstream. Answering those from a spreadsheet meant someone rebuilding a summary by hand every cycle, and the summary was stale the moment it was pasted into a pack.
Approach
- Prototype on dummy data first. Building on live programme data was never an option for a demo, so the first job was a dataset that behaved like a real RAID log without containing anything real. It meant the prototype could be shown to anyone without a single redaction.
- Two pages, two questions. Current Position for triage today. Mitigation Journey to judge whether risk management is real or theatre.
- All logic in measures. Base measures for counts and scores, time intelligence over snapshot dates, and inherent against residual comparisons. Every figure on the page traces back to one definition.
Outcome
The Deputy Head of PMO endorsed the prototype and it was taken forward, with named ownership of RAID reporting written into the PMO operating model. Version 3 is now built, three pages covering the current position, the RAID review meeting and issues, with a takeaway line on each page written in DAX from the live numbers. It runs on an export of the RAID log for now, with the live SharePoint connection as the next phase.
Lesson
Reporting earns trust when the reader can get from a headline number to the item behind it in two clicks. No static document can offer that, however well it is formatted.